Monday, March 26, 2012

Monday,, March 26...Things are happening!

Things are really starting to move now!  As you have probably seen the sidewalks are coming out, the water line for the sprinkler system was put in last Friday and the big news is that starting Tuesday the old armory side of the building will be coming down!

Items for this week (March 26-30):

· Monday through Wednesday demolition of the old armory side of the building.  Kids Kove will be closed these 3 days.  The scheduled start time for the building to come down is on Tuesday.  We don’t have an exact time yet but if you want to come and witness history it will be on Tuesday!

· A temporary sidewalk will be put in on Monday or Tuesday.  This will be for the change in entrance during the construction.  Our new entrance for the next 4 months will be down by the locker rooms.  We’ll ask members to enter through the current emergency exits.


Items for next week (April 2-6):

· The entire front of the building will be fenced off.

· The entrance will move to the south end of the building (watch for signs).

· The gymnasium will be closed during spring break week.  Kids Kove will be moving into the 4K room as there is no 4K during spring break.

· In the gym the old air handling unit will be removed that was with the old steam boiler, which also will be removed and replaced with energy efficient roof top units.

· Footings will also be poured during the week.

· The front internal vestibule will be removed.

If you have any questions please feel free to give me Darian Blattner a call at 246-2252 or e-mail at dblattner@nracentre.com. 


No comments:

Post a Comment