Wednesday, May 23, 2012

May 23rd Update
 

Dear Centre Member:

The outside portion of construction is nearly complete.  In the next two weeks the inside work will begin and you will see more changes to the facility.  The best news is the work is on schedule!

Here is what has happened in the last couple of weeks:

· The outside masonry has been completed and only a few touch up spots remain.

· Windows have been installed in the new areas.

· Rooms have been framed up and insulation is starting to go in.

· The roof has been installed with only a few touch up spots to finish.

· Plumbing, Electrical and HVAC work is on-going.

· Most of the parking lot has been cleared up for members to resume parking.

· The landscaping was installed by Backyard Paradise Landscaping!


Items for the coming weeks:

· Doors into the new community rooms will be saw cut at night this week.

· More temporary walls will be installed for the old vestibule to be removed.

· The new front vestibule will be constructed.

· The walls in the new areas will all be sheet rocked.


We do have one request of our members and this comes from our surrounding neighbors.  Whenever possible we ask our members to park in one of the parking lots and not on the side streets.  Our neighbors have expressed some frustration with people parking in front of their homes and driveways and they have concerns with safety as the streets fill up.  We are working with Derrick Companies to help keep the parking lots clear in the evenings so if you can please try and park in the lots before going onto the side streets.  Our neighbors will appreciate it!

If you have any questions please feel free to give me a call at 246-2252 or e-mail me at dblattner@nracentre.com.  With all the events and activities going on it’s easy to forget to share things so please do not hesitate to contact me with any questions you might have.  You can also keep up to date with construction happenings, including pictures through our website at www.nracentre.com.

Sincerely,

Darian Blattner

Executive Director



3 comments:

  1. How are the updates coming? I'm DEFINITELY not coming to the Centre until they are complete. Period.

    ReplyDelete
  2. Sorry about my prior post. I've had a REALLY bad day on account of a car repo and an infected dragon tat on my right calf.

    ReplyDelete
  3. By the way, what is the Centre's policy on swimming with skin infections? The swelling is really starting to come down, and there is minimal pus.

    ReplyDelete